Garfield

  • Garfield Elementary School
    Original Construction Date: 1953

Project Updates

  • Garfield Elementary Schoolgraph showing percent spent

    Total Budget: $1,578,700.00
    Contracted to Date: $1,534,600.00

    Last Updated: 02/13/2023

    Status
    Bond Project
    Scheduled
    Completed
    ✓ 
    Asbestos Abatement & Inspection
    2021
    2021 
    ✓ 
    Roof Repair / Replacement
    2021
    2020 
    ✓ 
    Fire System Upgrade
    2021
    2021 
    ✓ 
    Playground Safety Improvements
    2021
    2020 
    ✓ 
    High Impact Building Improvements
    2021
    2021