Berthoud

  • Berthoud Elementary School
    Original Construction Date: 1962
  • Berthoud Elementary School graph showing percent spent 

    Total Budget: $5,181,900.00
    Contracted to Date: $4,892,300.00

    Last Updated: 02/13/2023

    Status
    Bond Project
    Scheduled
    Completed
     ✓
    Security Upgrades
    2020
    2020
     ✓
    Classroom Addition
    2020
    2020 
     ✓
    Asbestos Abatement & Inspection
    2020
    2020 
     ✓
    Drainage Improvements
    2020
    2020 
     ✓
    Roof Repair / Replacement
    2020
    2020 
     ✓
    Boiler Replacement & Improvement
    2020
    2020 
     ✓
    High Impact Building Improvements
    2020
    2020